Owner: Chongqing Sanfeng Zhengxing Environmental Energy Co., Ltd.
Preparation Period: 2024
Project Overview: Access system design is carried out for the municipal solid waste comprehensive treatment domestic waste incineration power generation project (2×15 MW) in the Bishan Waste Green Circular Economy Industrial Park, including access location, number of access circuits, voltage level, etc. Relevant electrical calculations, power flow calculations, and conductor selection and verification are also conducted.