Construction Period: August 2026 – November 2026
Project Overview: Using a cooperative rooftop area of 637 m², the project involves the procurement of N-type monocrystalline silicon bifacial 630Wp modules, a 40kW string inverter, and main equipment such as a 40kW-80A grid connection box, to build a distributed photovoltaic power generation project with a DC-side capacity of 51.03kWp and an AC-side capacity of 40kW. After completion, the average annual power generation in 2025 is expected to be 37,400 kWh. The power consumption mode is self-generation for self-use, with surplus power fed into the grid.