Owner: Chengdu Xingrong Renewable Energy Co., Ltd.
Design Period: 2024
Project Content:
Overhead Line Section: The project starts from the 220 kV outgoing bay of the proposed Wanxing Phase III 220 kV Step-Up Substation and ends at the 220 kV incoming line gantry of the existing Hongsha 220 kV Substation. The entire line is a single-circuit overhead line with a route length of approximately 17.51 km, including 52 newly built single-circuit towers. The conductor type is JL3/G1A-300/25 steel-cored high-conductivity aluminum stranded wire, and the ground wire consists of two 48-core OPGW-100 optical cables.
Cable Section: The newly built cable route length is approximately 2.87 km. The cable type is ZC-YJLW03-Z 127/220 kV 1×500 mm² cross-linked polyethylene insulated, corrugated aluminum-sheathed, polyethylene-jacketed, longitudinally water-blocked power cable.