220 kV Outgoing Line Project of Chengdu Wanxing Environmental Protection Power Plant Phase III

Owner: Chengdu Xingrong Renewable Energy Co., Ltd.

Design Period: 2024

Project Content:

Overhead Line Section: The project starts from the 220 kV outgoing bay of the proposed Wanxing Phase III 220 kV Step-Up Substation and ends at the 220 kV incoming line gantry of the existing Hongsha 220 kV Substation. The entire line is a single-circuit overhead line with a route length of approximately 17.51 km, including 52 newly built single-circuit towers. The conductor type is JL3/G1A-300/25 steel-cored high-conductivity aluminum stranded wire, and the ground wire consists of two 48-core OPGW-100 optical cables.

Cable Section: The newly built cable route length is approximately 2.87 km. The cable type is ZC-YJLW03-Z 127/220 kV 1×500 mm² cross-linked polyethylene insulated, corrugated aluminum-sheathed, polyethylene-jacketed, longitudinally water-blocked power cable.

Contact us

Leave a message
Phone +86 023-67027293 / +86 18996196891
Email gridspower@qq.com
WeChat Company Official Website
Chat Chat
Back to top

Contact Us

Leave a message